Implementation of building information modelling application on qto work and scheduling simulator using tekla structure (project spk tower plant 3a) / Dahlia Inatsan Latifah

Latifah, Dahlia Inatsan - Nama Orang;

Abstrak
The construction industry 5.0 requires collaboration between field workers and technology in the form of software that can be collaborators in increasing the efficiency of the quality of construction work results. These demands are realized in the form of BIM technology with a digital-based modeling system that covers all work information on a project especially in calculating Quantity and scheduling. In contrast to the demands of the construction industry 5.0 era in Indonesia the application of BIM has not yet developed its application. This study aims to implement BIM to find out how much difference there is between the calculation of BOQ volume/quantity with the BIM approach using Tekla Structure software with BOQ quantity and how BIM is applied in making scheduling and scheduling simulations. The design of this research flow starts from creating 3D modeling extracting the volume of quantity/volume elements analyzing the calculation results compared to BOQ quantity how much difference occurs analyzing the duration of work using Tekla structure based on project data modeling simulator. Based on the results of the study the percentage difference in the calculation results of the concrete volume between the BOQ and BIM approaches was 0.12% while the reinforcement was 0.21% which means that the results of the study are in the Appropriate category because the percentage difference is in the range of 0-10%. with the results of the BIM simulator being able to describe the real conditions and progress of a job in 3D format this will certainly make it easier for workers to understand the progress and sequence of work on a project.


Informasi Detail
DDC
TUGAS AKHIR DIGITAL
Prodi
Universitas Negeri Malang. Program Studi Teknologi Rekayasa dan Pemeliharaan Bangunan Sipil, 2025.
Deskripsi Fisik
xi, 71 hlm. : ilus.
Bahasa
No Reg
0024/TA/25
Edisi
Tugas Akhir (Diploma)--Universitas Negeri Malang. 2025
Subjek
1. APLIKASI PEMODELAN INFORMASI BANGUNAN
2. BUILDING INFORMATION MODELING APPLICATION

Pembimbing
1. Drs. Nemesius Bambang Revantoro, M.t.
Lampiran Berkas
You must be logged in to get fulltext


UPT Perpustakaan UM
  • Berita

Tentang Kami

TIM IT Perpustakaan 2023

Cari

masukkan satu atau lebih kata kunci dari judul, pengarang, atau subjek

Donasi untuk SLiMS

Pilih subjek yang menarik bagi Anda
  • Karya Umum
  • Filsafat
  • Agama
  • Ilmu-ilmu Sosial
  • Bahasa
  • Ilmu-ilmu Murni
  • Ilmu-ilmu Terapan
  • Kesenian, Hiburan, dan Olahraga
  • Kesusastraan
  • Geografi dan Sejarah
Icons made by Freepik from www.flaticon.com
Pencarian Spesifik