Tugas Akhir

Studi perbandingan Rencana Anggaran Biaya (RAB) pekerjaan kolam renang ditinjau dari Rencana Anggaran Pelaksanaan (RAP) pada pembangunan kolam renang pendidikan Pertamina - Universitas Negeri Malang / Sutrisno Dwi Atmojo

Atmojo, Sutrisno Dwi - Nama Orang;

Abstrak
ABSTRACT Atmojo Sutrisno Dwi.2011.Comparative Studies of Rencana Anggaran Biaya (RAB) Reviewed The Rencana Anggaran Pelaksanaan (RAP) on The Development of a Education Swimming Pool PERTAMINA State University of Malang.The Finished Project a Course of Study D3 of Civil Engineering and Building The Faculty of Technical an State University of Malang.Tutorship Drs. N.Bambang Revantoro S.T. M.T. Keywords budget costs comparative analysis 12288 12288 12288 Construction of Education Swimming Pool PERTAMINA - State University of Malang (UM) is conducted by PT. Prambanan Dwipaka planning is done by CV Multisegaris Engginering. Studies in this final project aims to find out the comparative cost budget planning and execution on the work swimming pool. 12288 12288 12288 The data collected by means practice industry and interview.Data done two phases the first data is collected by method of observation to know the budget costs which includes volume work prices and wages office as well as analysis work.The second stage data is collected by method an interview to receive explanation about the budget analysis expenses used. 12288 12288 12288 The result showed the budget charge of the work pond in rencana anggaran biaya (RAB) Rp.2.594.862.000 00 (two billion five hundred ninety four million eight hundred sixty two thousand rupiah) while on the anggaran biaya pelaksanaan (RAP) Rp.2.352.861.000 (two billion three hundred fifty two million eight hundred sixty one thousand rupiah). 12288 12288 12288 Based on the results of the research the difference cost budget planning and budget execution cost is the price of the units of each of the different pekerjaaan. So the difference amount of budget cost of work a significant pool where anggaran biaya perencanaan (RAB) outweigh the costs of anggaran biaya pelaksanaan (RAP).


Informasi Detail
DDC
Rp 797.200681 ATM s
Prodi
Universitas Negeri Malang. Program Studi Teknik Sipil dan Bangunan, 2011.
Deskripsi Fisik
viii, 36 lembar : il., tab. ; 30 cm
Bahasa
Indonesia
No Reg
00976/KI/14
Edisi
Tugas Akhir (Diploma)-- Universitas Negeri Malang, 2011
Subjek
1. KOLAM RENANG - RENCANA ANGGARAN BIAYA
Pembimbing
1. N. Bambang Revantoro
Lampiran Berkas
You must be logged in to get fulltext


UPT Perpustakaan UM
  • Berita

Tentang Kami

TIM IT Perpustakaan 2023

Cari

masukkan satu atau lebih kata kunci dari judul, pengarang, atau subjek

Donasi untuk SLiMS

Pilih subjek yang menarik bagi Anda
  • Karya Umum
  • Filsafat
  • Agama
  • Ilmu-ilmu Sosial
  • Bahasa
  • Ilmu-ilmu Murni
  • Ilmu-ilmu Terapan
  • Kesenian, Hiburan, dan Olahraga
  • Kesusastraan
  • Geografi dan Sejarah
Icons made by Freepik from www.flaticon.com
Pencarian Spesifik