Analisa kinerja alat berat excavator type PC 300 pada pelaksanaan pekerjaan galian spillway proyek pembangunan Bendungan Tugu Trenggalek / Yulita Dian Andriana

Andriana, Yulita Dian - Nama Orang;

Abstrak
ABSTRAK Andriana Y. D. 2017. Analisa Kinerja Alat Berat Excavator Type Pc 300 Pada Pelaksanaan Pekerjaan Galian Spillway Proyek Pembangunan Bendungan Tugu Trenggalek . Tugas Akhir Program Studi D3 Teknik Sipil dan Bangunan Fakultas Teknik Universitas Negeri Malang. Pembimbing Drs. Boedya Djatmika S.T. M.T. Kata kunci analisis produktifitas excavator dump truck spillway proyek Bendungan Kabupaten Trenggalek Spillway merupakan salah satu komponen bangunan pada bendungan. Untuk mendapatkan konstruksi ini kontraktor harus melakukan pekerjaan galian tanah Pekerjaan galian tanah biasanya melibatkan beberapa jenis alat berat antara lain excavator dan dump truck. Dalam pelaksanaanya pengoperasian alat tersebut dipengaruhi oleh beberapa kondisi salah satunya adalah kondisi normal. Kajian ini dilaksanakan untuk mengetahui (1) produktifitas excavator pekerjaan galian tanah untuk spillway (2) capaian kerja dump truck dan excavator pekerjaan galian tanah untuk spillway dan (3) kriteria prestasi kerja alat berat excavator dan dump truck. Pengkajian ini hanya terkhusus pada saat cuaca normal pekerjaan galian tanah untuk Spillway pada proyek Bendungan Tugu Kabupaten Trenggalek. Pengkajian ini dilakukan dengan studi literatur observasi dan dokumentasi. Berdasarkan hasil pengkajian diketahui bahwa (1) produktifitas excavator pada pekerjaan galian tanah untuk spillway sebesar 773 65 m3/jam (2) Pada kondisi alat ideal atau sesuai perencanaan (9 dump truck) capaian kerja sebesar 355 32 m3/hari. Sedangkan pada pengoperasian alat riil (dilapangan) yaitu 5-6 dump truck sebesar 233 22 m3/hari dan (3) kriteria prestasi kerja alat berat excavator dan dump truck adalah negatif. Baik menggunakan perbandingan antara produktivitas lapangan dan produktivitas ideal yaitu nilai deviasi sebesar -120 6 m3/minggu maupun perbandingan antara produktivitas lapangan dan curva S dengan nilai defiasi -2322 7 m3/minggu. ABSTRACT Andriana Y. D. 2017. Performance Analysis Of Weight Excavator Type Pc 300 On Implementation Of Spillway Galler Projects Development Project Tugu Trenggalek. Project. Final Project D3 Program of Civil and Building Engineering Faculty of Engineering State University of Malang. Supervisor Drs. Boedya Djatmika S.T. M.T. Keywords analysis productivity excavator dump truck spillway project of District Dam Trenggalek Spillway is one component of building on dam. To get this construction contractors have to do the work of soil excavation Land excavation work usually involves several types of heavy equipment such as excavators and dump trucks. In the implementation of the operation of the tool is influenced by some conditions one of them is a normal condition. This study was carried out to find out (1) excavator performance for spillway (2) achievement of dump truck and excavator for spillway and (3) performance criteria of excavator and dump truck. This assessment is only specialized during the normal weather of excavation work for Spillway at the Tugu District Trenggalek District project. This study was conducted with literature study observation and documentation. Based on the result of the assessment it is known that (1) the excavator productivity at the ground excavator for spillway is 773 65 m3 / hour. (2) In ideal condition or according to plan (9 dump truck) work achievement 355 32 m3 / day. While in operation of real equipment (field) that is 5-6 dump truck equal to 233 22 m3 / day and (3) criterion of work performance of excavator and dump truck is negative. Good use of comparison between field productivity and ideal productivity that is deviation value equal to -120 6 m3 / week and comparison between field productivity and curva S with defiation value -2322 7 m3 / week.


Informasi Detail
DDC
Rp 629.225 AND a
Prodi
Universitas Negeri Malang. Program Studi Diploma III Teknik Sipil dan Bangunan, 2017.
Deskripsi Fisik
xii, 63 lembar : il. , tab. ; 30 cm
Bahasa
Indonesia
No Reg
04624/KI/17
Edisi
Tugas Akhir (Diploma)--Universitas Negeri Malang. 2017
Subjek
1. ALAT BERAT
2. EXCAVATOR

Pembimbing
1. Boedya Djatmika
Lampiran Berkas
You must be logged in to get fulltext


UPT Perpustakaan UM
  • Berita

Tentang Kami

TIM IT Perpustakaan 2023

Cari

masukkan satu atau lebih kata kunci dari judul, pengarang, atau subjek

Donasi untuk SLiMS

Pilih subjek yang menarik bagi Anda
  • Karya Umum
  • Filsafat
  • Agama
  • Ilmu-ilmu Sosial
  • Bahasa
  • Ilmu-ilmu Murni
  • Ilmu-ilmu Terapan
  • Kesenian, Hiburan, dan Olahraga
  • Kesusastraan
  • Geografi dan Sejarah
Icons made by Freepik from www.flaticon.com
Pencarian Spesifik